If you've driven Wycliffe Avenue between St. Johns Drive and Lakeside Drive, you've crossed the top of a dam. That raised stretch of pavement holds back Connor Lake. The Town of Highland Park says the roadway, the dam and the infrastructure along that corridor are rated "high hazard" by the Texas Commission on Environmental Quality. People Newspapers reported that under national dam safety standards, that rating means a failure is expected to cost lives.
Under the town's schedule, the full closure took effect the morning of Nov. 10, and the town expects the closure to last 20 to 24 months. Crews are removing the dam between St. Johns and Lakeside and building a bridge in its place. It's the second time this year the town has reworked one of its lakes as flood infrastructure, and the first job wrapped up just three months ago.
A Road That Was Never Built to Carry Storm Water
The Dallas Morning News reported that the section of Wycliffe between St. Johns and Lakeside acts as a dam but can't carry storm runoff. Residents raised the problem at a town hall in 2024. The new design adds a weir, a low dam that water can flow over. The town says the rebuilt crossing is "engineered to withstand a 100-year storm event," and the goal is to move the site from a "high hazard" rating to "low hazard."
The lake itself is meant to stay. The town's project FAQ says the work aims to keep Connor Lake at its current water level.
The FAQ also lists the work happening underground, which helps explain the long timeline. It includes the town's 30-inch Turtle Creek interceptor, town water and wastewater lines, City of Dallas water and wastewater lines, and relocations by Oncor, Atmos, AT&T and Spectrum. That's a lot of separate utilities, all to be rerouted under a two-lane crossing next to a lake.
What Is Closed, and Where Access Continues
The full closure covers Wycliffe from Abbott Avenue to Oak Lawn Avenue. The cross streets at Lakeside Drive, St. Johns Drive and Turtle Creek Boulevard are affected too, though the town says not all areas will be affected at the same time.
| Street or area | What the town has said |
|---|---|
| Wycliffe Avenue, Abbott to Oak Lawn | Fully closed starting Nov. 10, for 20 to 24 months |
| Wycliffe at Lakeside Drive, St. Johns Drive and Turtle Creek Boulevard | Intersections closed, with restrictions coming in phases |
| Fitzhugh Avenue | Closures or restricted access during some phases |
| Streets next to the work zone | Access and parking limited to residents; deliveries, visitors and emergency services keep access |
The closure is less than a mile from Fitzhugh Avenue and Central Expressway, and the Dallas Morning News says it's expected to increase traffic. Drivers, cyclists and pedestrians are asked to plan other routes and allow extra time, especially at peak hours. The town posted neighborhood route maps in late October, including a Lakeside Drive route map. Phase-by-phase detours will be posted on the Wycliffe Avenue Reconstruction Project page.
Updates will come through the project website, the town website, social media, newsletters and Blue Zone notifications. The town also has an owner's representative on site who serves as a direct contact for neighbors. If you live along Lakeside, St. Johns or Turtle Creek, sign up for Blue Zone alerts. That's how you'll hear when a phase moves onto your block.
Exall Lake Was Rebuilt for Flooding First
The town's other lake project for flood control finished on Aug. 1. Highland Park spent $2.5 million dredging Exall Lake. Starting in March, up to three barges circled the lake and pumped about 35,000 cubic yards of sediment into geotextile bags. That's roughly 130 years of buildup, according to People Newspapers.
The dredging served wildlife and drainage alike. Exall Lake is a stormwater channel, and the dredging was meant to keep storm water from flooding Riverside Drive. Lt. Lance Koppa of the Highland Park Department of Public Safety explained it to People Newspapers:
"If 40% of this waterway is silt, that water that's coming down starts not to have a place to go."
Exall and Connor are two parts of the same Turtle Creek drainage system. One lake got its capacity back this summer, and the other is now getting a crossing built to let a major storm through. Even some park walkways sit on top of this water-control system. The town's project records note that the pedestrian bridge in Lakeside Park was built in the 1940s on top of Exall Dam and was later rehabilitated.
Exall Lake is also the nearest place to see the finished results while Wycliffe is under construction. People Newspapers describes it as a stop for cyclists, with mallards, Chinese geese and turtles on the water and catfish, largemouth bass and bream below. The town plans to check the lake's condition every year to track how much sediment comes back. "This is not a one-and-done project," Koppa told the paper.
More changes may be coming. At an Oct. 20 study session, the Town Council reviewed a proposed long-term maintenance plan for Exall Lake. It included oxygenation and silt management, possibly three small fountains that might be lit with white or multicolor LEDs, aquatic plants and fish stocking. People Newspapers reported these as discussion items.
The Street That Comes Back Will Be Narrower
When Wycliffe reopens, it will have two lanes instead of three, with a dedicated left-turn lane across the bridge, much like the turn lane there now. The town says it ran traffic models to answer neighbors' concerns, and they showed no significant change in traffic flow with the new layout. The project also includes better pedestrian paths and landscaping along the corridor.
Here are the numbers behind it, from the council's Sept. 15 meeting as reported by People Newspapers:
- Contract: $22,205,303, awarded to low bidder Rebcon.
- Local share: about $6.2 million paid by Highland Park taxpayers. The rest comes from other sources, which the Dallas Morning News says include the Texas Department of Transportation.
- Design: Kimley-Horn prepared the renderings and project maps for the town.
- Same meeting: the council also authorized contracts to rebuild Eastern Avenue and Douglas Avenue and for the 2026 Drainage Easement Improvements Project.
Lance Koppa, the town's community and media relations manager, told the Dallas Morning News that Wycliffe is one of "the most significant infrastructure initiatives in Highland Park history." When you add up the dam rating, the lake level, the utility work and the turn lane, it's easy to see why.
Getting Around While the Bridge Goes In
For short trips across town without a car, there's Highland Park On-Demand, which the town started in May 2026 after leaving DART. Via runs the service under a six-month, fare-free pilot. At the Oct. 20 study session, the council heard that riders had taken more than 8,400 trips and rated the service 4.9 out of 5 on average.
As of that session, it ran from 5 a.m. to midnight, seven days a week. It's designed mainly for former DART riders, and council members talked about cutting hours and possibly charging riders who didn't previously use DART. Town Administrator Tobin Maples said staff recommended continuing the program. The pilot is near the end of its six-month run, so check the town's microtransit page for current hours and fares before you count on a ride.
If you're on foot or on a bike, the Exall Lake shoreline is a good place to see the town's flood work up close until the new Wycliffe bridge opens sometime in 2028.
Projects like this raise questions on the blocks closest to them, from how a phased closure affects a planned move to what a buyer will see on Lakeside Drive next spring. If you live near Turtle Creek and want to talk through what the Wycliffe timeline means for your street, in English or Spanish, Ana Candido is glad to help. Let's Connect.